Owner Tools · Planner

Permit Timeline Expecter

The question every owner asks second, that should be asked first: how long until I can legally start building? Pick your situation and watch a realistic schedule draw itself — drawings to permit in hand.

Inputs

Your situation

Major ≈ Salt Lake City. Suburban ≈ most of Davis, Weber, Utah County. Small ≈ towns where the plans examiner knows your name by round two.

Restaurants add a health-department review; medical adds engineering complexity that slows the drawing phase.

Retail becoming a restaurant, warehouse becoming a gym — changing the use can trigger planning & zoning review before building review even starts.

Expected schedule · weeks

Drawings to permit

Total: 7 – 15 weeks

Ranges from recent Davis and Salt Lake County experience. Every jurisdiction moves at its own speed, staffing changes it monthly, and a sharp design team compresses it. Confirm with your city — or ask us; we probably pulled a permit there last quarter.